HUNDREDS of Crossrail workers have walked out after being offered £400 a day to help finish Spurs’ delayed new stadium.

The contractors, mostly electricians, downed tools after pay talks collapsed on the train project — which is running two years behind schedule.

Getty – Contributor The builders of Spurs’ new stadium are offering £400 for Crossrail workers to join them

Getty – Contributor The White Hart Lane construction team are now making more money than the whole the Spurs squad, headed by Harry Kane

Crossrail is already two years behind schedule and the budget has increased from £14.8 billion to £15.4bn

They headed to North London, where an army of 3,800 workers are working round the clock on Tottenham’s £850million ground.

The construction team is now thought to be costing more in wages than the entire Tottenham squad, headed by Harry Kane.

A source said: “You’ve got 3,800 operatives down there in two shifts and whatever overtime they want.

“There’s 600 electricians on site and thousands of other trades. Being conservative that’s going to rack up at an average of at least £1,000 a week per head in labour.”

Experience the atmosphere inside the new Tottenham Hotspur Stadium before it even opens in FIFA 19 video

PA:Press Association Crossrail is expected to carry 200 million passengers a year

That would mean the total weekly wage bill is £3.8million — whereas the equivalent for the whole Spurs squad was around £2.4m last season.

The workforce is expected to be on site for six weeks at least, with some electricians contracted until November. Both the stadium and Crossrail projects have been dogged by problems. Spurs promised to play their first game at the new 62,000-capacity ground against ­Liverpool this Saturday.

But it was hit by a catalogue of delays, including a chronic lack of electricians. The game has now been switched to Wembley — along with several other fixtures.

Meanwhile, London’s 73-mile east-west Crossrail scheme was originally scheduled to open last year but will now not be finished until next autumn.

Getty – Contributor 3,800 contractors are working around the clock to finish New White Hart Lane

The budget for the project — expected to be used by 200 million passengers a year — has also increased from £14.8billion to £15.4bn due to “cost pressures”.

Hundreds of workers have walked out after talks on an equal pay deal for all contractors — plus a negotiated bonus — ended without agreement.

Tottenham 3-1 Fulham: Harry Kane scores his first August goal as strikes from Kieran Trippier and Lucas Moura complete win

Another source said: “This hasn’t happened overnight. It’s been more of a gradual, but consistent, drift. A lot of it has been done by word of mouth.”

Last night Unite union officer Guy Langston said: “It is of little surprise workers have been leaving Crossrail and seeking work on Spurs’ stadium.

“From the outset Unite sought a major projects agreement with Crossrail to ensure that a negotiated bonus and equal pay would apply across all contractors.

AFP or licensors The Unite union has tried to sign an agreement with Crossrail so bonuses and equal pay is applied to all contractors

“Crossrail refused to enter into such an agreement. They are reaping what they have sown.

“The number of electricians upping sticks has been greatest on the sections of the project operated by contractors such as Laing O’Rourke and Skanska.”

He accused them of “adopting a non-negotiated bonus scheme for their workers, far inferior to the Unite-negotiated scheme”.